2025-26 Construction Schedule
Brighton Construction Schedule
Brighton Construction Schedule for the week of Jan. 19 to 23
Below is the anticipated schedule of work from January 19 to 23, 2026.
Brighton High School
Technology Suite:
- Shelving installation
- Furniture installation
- Shop equipment connections
- Dust Collector start-up
- Fire alarm wiring
- Sink installation
Door 20 Addition:
- Subject to material arriving onsite, countertop and window jamb installation
Music Suite:
- Abatement
Athletic Fields and New Entry Lane:
- Subject to material arrival, there will be placement and installation of stone for new entry lane, drop-off loop and temporary laydown area which is next to the Buildings and Grounds Lot
- Weather-dependent stripping of topsoil, stockpiling onsite
- Demo and Disposal of Shed/House and utility removals
- Site prep including soil stockpiling and drainage work
Boiler Room:
- Mechanical and Plumbing piping disconnections
- Cooling Tower demo
- Structural steel demo
- Electrical disconnections
- Plumbing demo for sump pumps
Twelve Corners Middle School
STEAM Suite:
- Wall painting
- Millwork installation
- Data wire pulling AND fire alarm wiring
- Door Installation
Stairwells:
- Painting
Elevator:
- Electrical card reader programming
- Electrical panel work and testing
French Road Elementary School
Exterior Canopy:
- Electrical back-lit lighting installation for new signage
Main Lobby/Secure Vestibule:
- Dependent on material availability, metal coiling door install
Please note that our schedules are always subject to change based on many factors and opportunities including manpower, material availability, and weather.